DELTA TERMINAL C, LAGUARDIA REDEVELOPMENT PROJECT

New York, New York, USA

Image Courtesy: Corgan

Project Team:

Client: Delta Airlines, Port Authority of New York/New Jersey

Design Team: Corgan, BMcD, Aero, ARUP

Contractor: Delta Airlines

Project Description:

The New Delta Terminal Project at LaGuardia Airport in New York is a new terminal for Delta Air Lines that will replace their existing C and D Terminals. The new terminal will consist of 37 gates located on four concourses connected by a centralized check-in lobby, security checkpoint, and baggage claim. The gates will have access to dual taxi lanes, which will greatly improve airfield efficiency, resulting in reduced taxi time to and from the gate before take-off and after landing. The terminal will feature a new, larger Delta Sky Club with a Sky Deck, wider concourses, larger gate holdrooms and more seating, as well as 30 percent more concessions space than the existing Terminals C and D.

Roles and responsibilities

  • Designed the Delta terminal of New York’s LGA airport - Concourse G all the way from schematic design to construction documentation for both Core & Shell design & construction and Interior Fit out design & construction.

  • Conducted Level of Service (LoS) and passenger experience studies with a focus on Delta’s vision for the future for concourses D, E, F and G.

  • Created exhibits for the basis of design and environmental assessment reports that focus on community and ecological sustainability.

  • Documented and permitted life safety drawings for concourses D, E, F, G and headhouse.

  • Created exhibits for stakeholder engagement including virtual reality studies.